21st August
2009
It has been a busy week of renovations and many people have worked very hard to meet inspection deadlines so the work can continue without delay. Here are this week’s highlights from Kay Stewart:
- Successful wiring work day on Saturday resulted in rough wiring getting passed this week.
- The exterior red paint is disappearing.
- Building inspector gave us the go ahead to insulate and drywall interior walls.
- Roofers prepared the roof for the HVAC unit to be installed.
- Main stage and sound stage built.
- Plumbing contractor working in utility and children’s rooms.
- Nursery, stage and sound stage measured for carpet.
- Wonderful work session with 17 volunteers was held Thursday evening. Almost all the insulation was installed and a great start was made to the drywall!
Other Notes:
- Architect to clarify some revision issues with the city. Pray that this will not slow our process down. There is an issue with three revisions that were made.
- Drywall taping to start Monday.
- Kay learned what a “woofer” is.
Next Work Day: Saturday 8 – 4 - please bring a lunch! We need a crew to do wiring (2 to help Mike and others to do wiring for the sound); a large, strong crew to install drywall; and a couple of ladies to bring muffins.
Painting Crews are needed at the first of September – exact day to be determined.
THANK YOU all so much for the many willing workers who have helped thus far!